A. Within one day of receiving an application, the Department shall notify the applicant that the application is either complete or incomplete. If the application is incomplete, the notice shall specify what information is missing.
B. An applicant with an incomplete application shall supply the missing information within five days after the date of the notice. If the applicant fails to do so, the Department may deny the permit.
C. Upon receipt of all missing information within five days, as specified in subsection (B), the Department shall notify the applicant that the application is complete.
D. The Department shall not process an application for a permit until the applicant has fully complied with R2-11-403.
E. The Director shall render a permit decision no later than one day after receipt of a complete application. The date of receipt is the postmark date of the notice advising the applicant that the application is complete.
F. For the purpose of A.R.S. § 41-1073, the Department estab- lishes the following permit time-frames:
1. Administrative completeness review time-frame: one day.
2. Substantive review time-frame: one day.
3. Overall time-frame: two days.
Historical Note
New Section made by emergency rulemaking under
A.R.S. § 41-1026 at 9 A.A.R. 3046, effective June 18, 2003 for a period of 180 days (Supp. 03-2). Emergency
Section repealed and replaced by new Section under
A.R.S. § 41-1026(E) made by final rulemaking at 9
A.A.R. 3781, effective August 8, 2003 (Supp. 03-3).