Section R7-2-1105. Progress Payments  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • A.      Progress payments may be made by the school district to the contractor on the basis of a duly certified and approved esti- mate of the work performed during the preceding month if the contractor agrees to adhere to the provisions of A.R.S. § 41- 2577(B), (D), and (F). Payment shall be made within 14 days after the estimate of the work is certified and approved, except that a percentage of all estimates shall be retained as provided in R7-2-1104. The estimate of the work shall be deemed received by the school district on submission of the estimate of the work to the school district or a person designated by the school district for the submission, review or approval of the estimate of the work. An estimate of the work submitted under this Section shall be considered approved and certified after seven days from the date of submission unless before that time the school district or designee prepares and issues a specific written finding detailing those items in the estimate of the work that are not approved and certified under the contract. The school district may withhold an amount from the progress payment sufficient to pay the expenses the school district rea- sonably expects to incur in correcting the deficiency set forth in the written finding. No contract for construction may mate- rially alter the rights of any contractor, subcontractor or mate- rial supplier to receive prompt and timely payment as provided under this Section. On completion and acceptance of separate divisions of the contract on which the price is stated separately in the contract, payment may be made in full including retained percentages, less deductions, unless a substitute secu- rity has been provided pursuant to R7-2-1104.

    B.       Progress payments pursuant to subsection (A) are authorized for construction services contracts. The requirements of sub- section (A) apply only to amounts payable in a construction services contract for construction and do not apply to amounts payable in a construction services contract for design services, preconstruction services, finance services, maintenance ser- vices, operations services or any other related services included in the contract.

    C.      A subcontractor may notify the school district, in writing, requesting that the subcontractor be notified by the school dis- trict in writing within five days from payment of each progress payment made to the contractor. The subcontractor's request remains in effect for the duration of the subcontractor's work on the project.

    D.      If any payment to a contractor is delayed after the date due, interest shall be paid at the rate of one percent per month, or a fraction of a month, on such unpaid balance as may be due.

Historical Note

Adopted effective December 17, 1987 (Supp. 87-4). Sec- tion repealed; new Section made by final exempt rulemaking at 21 A.A.R. 1525, effective July 1, 2015

(Supp. 15-3).