Arizona Administrative Code (Last Updated: November 17, 2016) |
![]() |
Title 20. COMMERCE, FINANCIAL INSTITUTIONS, AND INSURANCE |
![]() |
Chapter 5. INDUSTRIAL COMMISSION OF ARIZONA |
![]() |
Article 4. ARIZONA BOILERS AND LINED HOT WATER HEATERS |
Section R20-5-409. Notification and Preparation for Inspection
All data is extracted from pdf, click here to view the pdf.
-
A. An authorized inspector shall perform a certificate inspection at a time mutually agreeable to the inspector and owner, user, or operator.
B. Before an authorized inspector performs an internal inspection of a boiler, an owner, user, or operator shall:
1. Cool the furnace and combustion chambers;
2. Drain the water from the boiler;
3. Remove the manhole and handhole plates, wash-out plugs, and inspection plugs in water column connections;
4. Remove insulation or brickwork if necessary to deter- mine the condition of the boiler, headers, furnace, sup- ports, and other parts;
5. Remove the pressure gauge for testing;
6. Prevent any leakage of steam or hot water into the boiler by disconnecting the involved pipe or valve;
7. Close, tag, and padlock the non-return and steam stop valves before opening the manhole or handhole covers and entering any part of the steam generating unit that is connected to a common header with other boilers. Open the free blow drain or cock between the non-return and steam stop valves;
8. Close, tag, and padlock the blowoff valves after draining the boiler: and
9. Open all drains and vent lines.
Historical Note
Repealed effective April 12, 1979 (Supp. 79-2). New
Section adopted effective April 9, 1992 (Supp. 92-2). R20-5-409 recodified from R4-13-409 (Supp. 95-1). Amended effective October 9, 1998 (Supp. 98-4).