Section R2-7-704. Refusal to Submit Cost or Pricing Data  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • A.      If an offeror fails to submit cost or pricing data in the required form and within the time-frames required, the agency chief procurement officer may reject the offer.

    B.       If a contractor fails to submit data to support a contract modifi- cation in the form required and within the time-frames required, the agency chief procurement officer may:

    1.        Reject the contract modification; or

    2.        Set the amount of the contract modification subject to the contractor’s rights under Article 9 of the Arizona Pro- curement Code.