Section R19-3-564. Controversies Involving Contract Claims Against the Lottery  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • A.      A claimant shall file a contract claim with the procurement officer within 180 days after the claim arises. The claim shall include the following:

    1.        The name, address, and telephone number of the claim- ant;

    2.        The signature of the claimant or claimant’s representa- tive;

    3.        Identification of the solicitation or contract number;

    4.        A detailed statement of the legal and factual grounds of the claim including copies of the relevant documents; and

    5.        The form and dollar amount of the relief requested.

    B.       The procurement officer shall have the authority to settle and resolve contract claims.

Historical Note

New Section R19-3-564 renumbered from R19-3-556 by final rulemaking at 19 A.A.C. 1641, effective August 4,

2013 (Supp. 13-2).