Section R18-1-505. Overall Time-frame Operation  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • A.      The overall time-frame for an application begins on the same day as the administrative completeness review time-frame.

    B.       The running of days within the overall time-frame suspends and resumes in concert with the administrative completeness and substantive review time-frames and time-frame extensions.

    C.      The duration of the overall time-frame equals the sum of all the following days  unless altered  by R18-1-508 (licensing time-frames pre-application agreements) or R18-1-511 (changed licensing time-frames agreements):

    1.        The lesser of:

    a.         The number of days shown for the administrative completeness review time-frame on the license tables, or

    b.        The actual number of days for the administrative completeness review time-frame if the Department notifies the applicant under R18-1-503(E) that the application is administratively complete before the expiration of the administrative completeness review time-frame;

    2.        The lesser of:

    a.         The number of days shown for the substantive review time-frame on the license tables,

    b.        The actual number of days for the substantive review time-frame if the Department notifies the applicant of a licensing decision under R18-1- 504(B)(1), or

    c.         The actual number of days for the substantive review time-frame if the applicant causes the time- frames to end under R18-1-507(D); and

    3.        The number of days added by one or more licensing time- frames extension agreements under R18-1-510.

Historical Note

New Section adopted by final rulemaking at 5 A.A.R. 3343, effective August 13, 1999 (Supp. 99-3). Amended by final rulemaking at 13 A.A.R. 1854, effective June 30, 2007 (Supp. 07-2).