Arizona Administrative Code (Last Updated: November 17, 2016) |
![]() |
Title 14. PUBLIC SERVICE CORPORATIONS; CORPORATIONS AND ASSOCIATIONS; SECURITIES REGULATION |
![]() |
Chapter 3. CORPORATION COMMISSION RULES OF PRACTICE AND PROCEDURE |
![]() |
Article 2. RULES OF PRACTICE AND PROCEDURE BEFORE POWER PLANT AND TRANSMISSION LINE SITING COMMITTEE |
Section R14-3-214. Review of committee decision
All data is extracted from pdf, click here to view the pdf.
-
A. Within five days of the issuance of a certificate of environ- mental compatibility, the Committee shall transfer a copy of said certificate along with its written decision, to the Corpora- tion Commission for its review and approval, subject to sub- section (B) hereof.
B. Within 15 days after the date the Committee has rendered its written decision any party to a certification proceeding may request a review thereof by the Corporation Commission.
C. Grounds for requesting review shall be stated in a written notice filed with the Corporation Commission with a copy thereof served on the chairman of the Committee and all par- ties to the certification proceeding.
D. Within five days of receipt of the notice referred to in subsec- tion (C) hereof, the chairman shall transmit to the Corporation Commission the complete record, including a certified tran- script.
Effective 2-70.